Name of the Milestone |
Planned deadline |
Actual Deadline |
A.1: Procurement procedures finished |
2013.11.15. |
2015.10.30 |
A.2: Technical plans completed HU |
2013.12.15. |
2014.07.30. |
A.3: Obtaining permissions |
2014.01.31. |
2014.05.14. |
2013.12.31. |
2013.09.19. | |
A.4: The last stakeholder consultation held |
2014.12.31. |
2016.07.19. |
C.1: Water reservoir created |
2014.12.31. |
2016.01.29. |
C.2: By-pass built |
2014.12.31. |
2016.01.29. |
C.3: Lake Kűvölgy #1 dredged |
2014.03.31 |
- |
C.3: Lake Kűvölgy #2 dredged |
2014.03.31. |
2015.12.15. |
C.4: Valley-closing barrage of Kűvölgy #3 built |
2014.12.31. |
2016.01.29. |
C.5: Valley-closing barrage of Kűvölgy #4 built |
2014.12.31. |
2016.01.29. |
C.6: First bottom threshold or step built |
2014.10.15. |
2016.01.04. |
C.6: 100 bottom thresholds or steps built |
2014.11.30. |
2016.01.15. |
C.6: 123 bottom thresholds or steps built |
2014.12.31. |
2016.01.29. |
C.7: Service roads reconstructed |
2014.12.31. |
2015.12.15. |
C.8: IAS control started |
2014.02.01. |
2014.03.03. |
C.8: IAS cleared off |
2014.12.31. |
2014.12.31. |
D.1: Sample parcels and quadrates defined |
2013.11.15. |
2014.04.30. |
D.1: Elaboration of one monitoring plan HU |
2013.10.15. |
2013.10.15. |
D.2: Socio-economic study ready |
2018.04.30. |
2018.12.31. |
E.1: Website is in operation |
2014.01.15. |
2014.02.28. |
E.2: Notice boards and gates installed |
2013.12.31. |
2014.04.30. |
E.3: Educational trail ready |
2016.06.30. |
2016.06.15. |
E.4: First press conference held |
2013.12.31. |
2013.12.04. |
E.5: Brochures published |
2016.09.30. |
2017.04.28. |
E.5: Flyer published |
2016.09.30. |
2017.04.28. |
E.5: Maps published |
2016.09.30. |
2017.04.28. |
2013.11.30. |
2013.11.06. | |
E.7: First guided excursion held |
2016.06.30. |
2016.07.28. |
E.7: T-shirts ready |
2016.03.31. |
2016.05.13. |
E.8: Layman's report published |
2018.08.31. |
2018.12.31. |
E.9: Post project communication plan ready |
2018.08.31. |
2018.12.31. |
E.10: International conference held |
2017.09.30. |
2018.05.28-30. |
F.1: Public procurement procedure for projectmanagement company started |
2013.10.01. |
2013.09.10. |
2013.11.15. |
2013.10.25. | |
F.2: First meeting of the Steering Committee held |
2013.12.31. |
2013.09.02. |
F.3: Training events held |
2013.12.31. |
2013.12.05. 2014.03.21. |
F.4: First international visit |
2016.06.30. |
2016.09.13-15. |
F.4: Project presented on a national conference |
2018.08.31. |
2015.03.24-26. |
F.5: Financial audit completed |
2018.08.31. |
2019.02.28. |