Name of the Milestone

Planned deadline

 Actual Deadline 

A.1: Procurement procedures finished

2013.11.15.

2015.10.30

A.2: Technical plans completed HU

2013.12.15.

2014.07.30.

A.3: Obtaining permissions

2014.01.31.
2015.03.31.

2014.05.14.
2015.08.17.

A.4: 1st stakeholder consultation held

2013.12.31.

2013.09.19.

A.4: The last stakeholder consultation held

2014.12.31.

2016.07.19.

C.1: Water reservoir created

2014.12.31.

2016.01.29.

C.2: By-pass built

2014.12.31.

2016.01.29.

C.3: Lake Kűvölgy #1 dredged

2014.03.31

 -

C.3: Lake Kűvölgy #2 dredged

2014.03.31.

2015.12.15.

C.4: Valley-closing barrage of Kűvölgy #3 built

2014.12.31.

2016.01.29.

C.5: Valley-closing barrage of Kűvölgy #4 built

2014.12.31.

2016.01.29.

C.6: First bottom threshold or step built

2014.10.15.

2016.01.04.

C.6: 100 bottom thresholds or steps built

2014.11.30.

2016.01.15.

C.6: 123 bottom thresholds or steps built

2014.12.31.

2016.01.29.

C.7: Service roads reconstructed

2014.12.31.

2015.12.15.

C.8: IAS control started

2014.02.01.

2014.03.03.

C.8: IAS cleared off

2014.12.31.
2015.12.31.
2016.12.31.
2017.12.31.

2014.12.31.
2015.12.31.
2016.12.31.
2018.10.31.

D.1: Sample parcels and quadrates defined

2013.11.15.

2014.04.30.

D.1: Elaboration of one monitoring plan HU

2013.10.15.

2013.10.15.

D.2: Socio-economic study ready

2018.04.30.

 2018.12.31.

E.1: Website is in operation

2014.01.15.

2014.02.28.

E.2: Notice boards and gates installed

2013.12.31.

2014.04.30.

E.3: Educational trail ready

2016.06.30.

2016.06.15.

E.4: First press conference held

2013.12.31.

2013.12.04.

E.5: Brochures published

2016.09.30.

2017.04.28. 

E.5: Flyer published

2016.09.30.

2017.04.28. 

E.5: Maps published

2016.09.30.

2017.04.28. 

E.6: First public information meeting held

2013.11.30.

2013.11.06.

E.7: First guided excursion held

2016.06.30.

2016.07.28.

E.7: T-shirts ready

2016.03.31.

2016.05.13.

E.8: Layman's report published

2018.08.31.

2018.12.31. 

E.9: Post project communication plan ready

2018.08.31.

2018.12.31. 

E.10: International conference held

2017.09.30.

2018.05.28-30. 

F.1: Public procurement procedure for projectmanagement company started

2013.10.01.

2013.09.10.

F.1: Project management company contracted

2013.11.15.

2013.10.25.

F.2: First meeting of the Steering Committee held

2013.12.31.

2013.09.02.

F.3: Training events held

2013.12.31.
2014.01.31.

 2013.12.05. 
2014.03.21.

F.4: First international visit

2016.06.30.

2016.09.13-15.

F.4: Project presented on a national conference

2018.08.31.

2015.03.24-26.

F.5: Financial audit completed

2018.08.31.

2019.02.28.